EPS Nodes & Project Files

No replies
Brian Walkin
User offline. Last seen 48 weeks 3 days ago. Offline
Joined: 27 Dec 2017
Posts: 33
Groups: None

I have certain data fields that apply to all of the projects within a node. Rather than maintinaing that data on each project schedule file it would make sense to manage them at the EPS node. However the fields available to the EPS Node are limited. 

I am able to add User Defined Fields which can be added to all nodes and project files but they are just text fields and it's not possible to control the data. 

Any ideas / guidance appreciated.

Santosh Bhat
User offline. Last seen 11 weeks 16 hours ago. Offline
Joined: 15 Apr 2005
Posts: 381

Brian,

Activity Codes are the ONLY feature that P6 explicitly allows to be set at EPS level.

Brian Walkin
User offline. Last seen 48 weeks 3 days ago. Offline
Joined: 27 Dec 2017
Posts: 33
Groups: None

Thanks, all. Seems you confirm my finding that Activity codes can't be applied at the EPS vevel, for now.

thanks

Santosh Bhat
User offline. Last seen 11 weeks 16 hours ago. Offline
Joined: 15 Apr 2005
Posts: 381

It could be so easy for Oracle to implement EPS level data, like Activity Codes, for 

-Calendars

-Resources

-Layouts, including filters.

With the security profile model as applied to the EPS it would be so much easier for users to manage their projects. This was presented to Oracle over a decade ago, But hey its Oracle - they know what we want better than ourselves.

david kelly
User offline. Last seen 7 weeks 1 day ago. Offline
Joined: 12 Feb 2016
Posts: 39
Groups: None

Brian,

Only Activity Codes have a version which is specific to an EPS node and its children. EPS codes are text only, so no arithmetic and to/from date arithmetic.

It is worth noting that if you use them, Export of projects require the receiving database to have EXACTLY the same EPS node structure to import EPS codes.

Rodel Marasigan
User offline. Last seen 11 weeks 6 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699

What sort of data set are your looking for? Is project codes will help?