Create Baseline & Update Schedule in P6 v7

5 replies [Last post]
Sahibzada Moqeem
User offline. Last seen 15 weeks 2 days ago. Offline
Joined: 21 Apr 2011
Posts: 6

Can anyone tell me the simple procedure on how to create baseline and once the baseline is saved then how to update the schedule.

Thanks.

Replies

Mushtaque Ali
User offline. Last seen 7 years 4 weeks ago. Offline
Joined: 14 Aug 2007
Posts: 9
Groups: GPC Qatar

Hope now your doubt is clear.

Mushtaque Ali
User offline. Last seen 7 years 4 weeks ago. Offline
Joined: 14 Aug 2007
Posts: 9
Groups: GPC Qatar

MAINTAIN BASE LINE :

First i am going to brief  you the Baseline can be create 

  • Current project as a Baseline
  • convert another project to new Base line       

Step 1.  Go to Project and select from the drop down maintain baseline and press add button then new window will be appear there you can select either you want to add 1. Current Project as Base line or Convert another Project as New Baseline Choise is yours

2119
maintain_baseline_1.jpg

 

2120
maintain_baseline_2.jpg

 

Step 2. Go to Project and select from the drop down Assign Baseline.

Step 3. Go to View and and select from the drop down Bars and tick the Primary Base line under disply. You should now see the Project baseline bar is displayed, generally bar colour is in yellow you can change as per your wish.

2121
maintain_baseline_3.jpg

Johannes Vandenberg
User offline. Last seen 8 weeks 5 days ago. Offline
Joined: 21 Jan 2010
Posts: 234

 

Hi Sahibzada

Is this what you are looking for ?

Try this; In P6 you have 3 steps to ensure that the baseline milestones are not shifting during updating the schedule.

Step 1: Go to maintain baseline and add new baseline. Give the baseline and clear identification. Say BASELINE APRIL 2012

Also make the BASELINE APRIL 2012 your PROJECT BASELINE. this is at the lower part of the same form

Step 2: Go to Assign baseline and assign the baseline BASELINE APRIL 2012. 

Step 3: Go to View bars and select the tick box for PROJECT BASELINE. 

You should now see that the PROJECT BASELINE bar is displayed , usually in a yellow color, under the green colored bars.

If you now update the schedule the yellow PROJECT BASELINE bars and milestones are remaining in the same position and the remaining duration bars these are color green are moving.

In short, maintain the baseline, assign the baseline and display the baseline

Johannes

Sahibzada Moqeem
User offline. Last seen 15 weeks 2 days ago. Offline
Joined: 21 Apr 2011
Posts: 6

Still didn't receive any reply!!!!

Sahibzada Moqeem
User offline. Last seen 15 weeks 2 days ago. Offline
Joined: 21 Apr 2011
Posts: 6

 

Can anyone tell me the simple procedure on how to create baseline and once the baseline is saved then how to update the schedule.

Thanks!

At your Early response!