Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Help!!! Duplicated Resources was not updated by using Baseline update utility in P6 8.2

2 replies [Last post]
David Cui
User offline. Last seen 5 years 30 weeks ago. Offline
Joined: 17 Jun 2015
Posts: 2

Hi All,

I had a problem with baseline update in P6.

I am one activity in current schedule with the same resource assigned several times and Zero out some existing resources. I tried to update the baseline for this activity with changed resources. However, after updating the baseline using the following setting:

5514
capture.png

 

The baseline budget is not updated properly and I saw that the existing duplicated resources in the baseline was only one of them left. This update actually removed the duplication. This is not what I wanted.

I would be very appreciated if someone have any solutions if anyone have suggestions?

Thanks for your help and I look forward to hearing from you.

David Cui

Replies

Zoltan Palffy
User offline. Last seen 2 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3091
Groups: None

David Kelly I would also like to see your solution

David Kelly
User offline. Last seen 2 years 49 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630

I know everything about this.  Baseline Update has never worked, still has issues in version 17.12, but the issues change with each version. I still have a guide for doing this with version 8.3.  Send me your contact details and I will send you the PDF file....