updating the baseline??need help

2 replies [Last post]
amit parmar
User offline. Last seen 16 years 24 weeks ago. Offline
Joined: 20 Feb 2007
Posts: 10
Groups: None
Hey,
I have a live project in which some activities have been added and resources assignments have been updated.but the project start and end dates are not matching and the budgeted cost has also changed.i need to get the baseline the same budgeted cost as the live project.

Initially i removed the actuals from the live project and tried to get the start and end dates to match.but i have not met with much success.

Any kind of help would be appreciated!!!!

Replies

A D
User offline. Last seen 3 years 23 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Hi amit,

If you dont have baseline program saved, then copy the updated project and then do the following

Go to Global Change and put

If AS Is Greater Than "Baseline date"
Then
AS = " "
AF = " "
PCT = = o

This will definitely help you

Somebody has given this post before, please check the previous links. You may get some good stuff.

Cheers,

Raviraj
Ashraf Jahangeer
User offline. Last seen 8 years 6 weeks ago. Offline
Joined: 8 May 2007
Posts: 144
Hi Amit,

I want to understand, dont you have a baseline schedule in place? Which is usually the case, we have a baseline and we have the live updated schedule.

If the answer is no then you can copy the live project and make a baseline (target). It will be bit of manual work to modify the updated project rsources and dates etc. Let us know the specific places where you face problem modifying the baeline manually.


Regards,


Ashraf