Need Help with Event Code: 90C0432B During Baseline Updates

2 replies [Last post]
JJ Aucoin
User offline. Last seen 23 weeks 3 days ago. Offline
Joined: 24 Jul 2002
Posts: 6
Groups: None

Hello fellow P6 gurus,

Can you assist me with my latest P6 issue??

Need Help with Event Code: 90C0432B    I keep getting this error message during my baseline updates.   Each time I press "Update" I get this message before it runs.

Trying to update my baseline to mirror the projects actual dates.

 

thanks,

Replies

Larry Cortez
User offline. Last seen 12 years 8 weeks ago. Offline
Joined: 8 Jan 2013
Posts: 12
Groups: None

Is this standalone or client-server?

Try going into C:\Program Files (x86)\Common Files\Primavera Common\Java and run the admin.cmd utility. Log in with privuser. In the window that opens, right-click on the INTERNAL_PLUGINS configuration and click Delete. Save and exit the utility. Close and relaunch Primavera and try running baseline update again.

Let me know if this works for you.

 

Regards,

Larry

litbusiness.com

Raymund de Laza
User offline. Last seen 41 weeks 5 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Hello P6 Users,

I encountered the same error and still was not able to sort out.

Anybody has the solution?

 

 

Regards,