Adding Resources using Global change

4 replies [Last post]
Haresh Jayanth
User offline. Last seen 6 years 9 weeks ago. Offline
Joined: 24 Aug 2006
Posts: 219
Hi Rodel,

Normally whenever i want to assign resources to set of activities , i export in excel and use fill cell to assign resources to activities.

In P3.1 , we have add option for resource in Global change, wherein we add resources for the selected activities.

In P6.0 am not able to see this option of adding a resource thru global change.....pls help out..

regards,

Haresh Jayanth

Replies

Haresh Jayanth
User offline. Last seen 6 years 9 weeks ago. Offline
Joined: 24 Aug 2006
Posts: 219
Thanks very much Rodel.

regards,

Haresh Jayanth
Rodel Marasigan
User offline. Last seen 1 day 8 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Haresh,
You need to change the subject area in order to select resource as per sample below.
GC Resource
Haresh Jayanth
User offline. Last seen 6 years 9 weeks ago. Offline
Joined: 24 Aug 2006
Posts: 219
Dear Rodel,

I have done Resource assignment by assign resource icon. But still i am not able to assign resource using Global change for selected activity......

In if criteria , i have given some criteria and in then criteria , i am trying to assign resources for the selected activities...but i am not able to get in the parameter column"Resource assignments" , can u help me out.

regards,

Haresh Jayanth
Rodel Marasigan
User offline. Last seen 1 day 8 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Haresh,
P6 is the same as P3. You can change the resource assignment using global change:
You have to change the subject area to Activity Resource Assignment and you find resource field once selected.

Note: P3 & P6 will be able to change resource assignment if there is existing resource. If there is no existing resource then you cannot add new resources to activity.

To Add resource to multiple selected activities, highlight all those activities and click assign resource icon on the right of the screen then select the resource you want to assigned and all activities selected will have the resource.

Best Regards,
Rodel