Hi Rodel,
Normally whenever i want to assign resources to set of activities , i export in excel and use fill cell to assign resources to activities.
In P3.1 , we have add option for resource in Global change, wherein we add resources for the selected activities.
In P6.0 am not able to see this option of adding a resource thru global change.....pls help out..
regards,
Haresh Jayanth