Spilit resource & Budgeted Units using Global change

1 reply [Last post]
Haresh Jayanth
User offline. Last seen 6 years 9 weeks ago. Offline
Joined: 24 Aug 2006
Posts: 219
Hi Rodel,

i have assigned only one type of resources to all activities called "Manpower".
Now my Engineer is instructing to split these resources into two separate resources i.e. 60% of resources to be assigned as skilled workers and 40% of resources to be assigned as unskilled workers.
For example , By the above split all the Budgeted units assigned for all activities by using "Manpower resources" if it has 100 Budgeted units should now read as Skilled workers Budgeted units "60" and unskilled workers Budgeted units "40" . This split should be assigned to all activities.
Is it possible to split these resources and their units for assigned resources by using Global change

regards,

Haresh Jayanth

Replies

Rodel Marasigan
User offline. Last seen 1 day 4 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Haresh,

Please read my response to the same query link below.
Copying Resouce