Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Price / Unit for Reosurces

5 replies [Last post]
Haresh Jayanth
User offline. Last seen 7 years 17 weeks ago. Offline
Joined: 24 Aug 2006
Posts: 219
Hi,

I have assigned two price / unit for a single resource under unit & prices i.e.

Effective date from 1st June - 2010 - Price / Unit - $ 120 / d & from 10th June 2010 Price / unit $ 150/d.

Suppose i am assigning this resources to an activity with start date of 5th June 2010 and completion date of 20th June 2010, Primavera should suppose to calculate based on my price/ unit upto 10th June 2010 with $120/d and from 10th June 2010 to 20th June 2010 the price / unit should be calculated by $150/d.......

But primavera calculates throught the activity duration with single Price / unit only i.e. $ 120/d??? Can anyone explain me why it is not taking Price / unit $150/d from 10th June 2010??

regards,

Haresh

Replies

Rodel Marasigan
User offline. Last seen 23 weeks 2 days ago. Offline
Joined: 25 Oct 2006
Posts: 1699
P6 will calculate Price/Unit as defined. If an activity have resource assigned and falls on different rate defined then it will used the rate that falls on the date define but will show only one rate with “*” but using average or linear distribution from start to finish date of activity. If resource are assigned repeatedly on one activity and change the planned date to align on the rate define then the distribution will be based on different rate defined but will show only original rate or the first rate define. If an activity fall on the resource rate alignment then the correct rate will be reflected.
Ex: Activity start 03-May-2010 and finish 21-May-2010 having on resource with different rate every 5 days (10, 20 & 30)
1) If assigned once using 10hrs/day will have a sum of 300 for the whole duration and distribute evenly from start to finish which is equal to 20 per day.
2) If a resource assigned three times and planned date is change to suit rate changes then it will distribute according to the rate define but will show only the first rate define.
3) If an activity is defined to suit rate changes then it will show correct rates.

Note: Make sure that recalculate assignment cost is refresh when rate changes to refresh the correct value.
Andrew Dick
User offline. Last seen 9 years 22 weeks ago. Offline
Joined: 14 Feb 2007
Posts: 295
Fair enough, It seems I stand corrected.
Maybe there is some setting in the project properties box which could effect this outcome.

May be worth a look tomorrow when I return to the widget factory.
Roger Booth
User offline. Last seen 5 years 26 weeks ago. Offline
Joined: 26 Oct 2006
Posts: 74
Groups: None
Forgot to mention though, the unit price shown in the activity screen bottom display does not change from the original unit price. It can be a bit confusing when the unit price multiplied by the remaining hours and the remaining cost do not appear to add up.
Roger Booth
User offline. Last seen 5 years 26 weeks ago. Offline
Joined: 26 Oct 2006
Posts: 74
Groups: None
I think that you will find that P6 changes the unit price to that in the resource screen at the dates identified.
I have got a fully resourced programme with estimated incremental rises every October 1st which runs for approximately 5 years. When updating the programme and an activity which was planned for before the increment al rise now straddles it, the value of that activity increases. I too thought that it would be too good to be true but it actually does it properly.
Andrew Dick
User offline. Last seen 9 years 22 weeks ago. Offline
Joined: 14 Feb 2007
Posts: 295
Haresh,
I will stand corrected if I’m wrong (I hope I am), but I understand that Primavera will price the whole activity based on the price of the resource at the start date of the activity.

Andy