Why does resource limit line varies

1 reply [Last post]
Haresh Jayanth
User offline. Last seen 6 years 9 weeks ago. Offline
Joined: 24 Aug 2006
Posts: 219
I have set a resource limit as Max/ Unit 1. But when i see this resource limit in resource profile, it shows fluctions (Zigzag line) and not a Straight line eventhough i have only set one max/unit to the resources .

How can it shows Zigzag limit line , if i set one max/ unit to that resource...

Replies

Rodel Marasigan
User offline. Last seen 12 hours 38 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699
If your calendar working hours is 8hr mon-fri and 4hrs sat plus other non working period like holiday make your limit as zizag.
Change your timescale to day/hour so you can understand your resource limit.