P6 shows links to baseline bars, not the open project’s
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hello guysss am working with interiors comany and please tell me how i give the relationship to activity i min how do i study on it
It's a interior I'D work ..........
Great thanks saved me so much angst worth belonging to PP just for that :-)
Thanks - its irritated the life out of me for the last 6 months
Aha! I had tried reordering the bars but must have left a baselines row higher than a current row somewhere, hence failing to shift the links. Now its spot-on.
Very much obliged for your continued support,
Adrian.
You need to make sure that the bars are in the correct order. If the baseline bar is listed before the current bar, it will draw the relationship on the baseline bar. Use the up and down arrows to change the order.
Strangely enough, some of the standard layouts have the bars in the wrong order and you dont notice until you turn on the baseline.
Ian
http://www.emerald-associates.com