Greetings,
Apologies if this issue has been raised before but with the PP search engine still down, I cant find a ready-made answer.
Has anyone found that P6.0 will display relationship lines amongst the baseline bars and milestones instead of the open projects bars and milestones? I cant find an option to force P6.0 to show relationships amongst the open project/s if Im displaying any type of baseline as well.
Ive found that any Gantt chart view options that include one or both of the primary baseline bars and primary baseline milestones will attract the relationship lines away from the open project bars and milestones.
The same happens for project, secondary and tertiary baselines.
Its very, very irritating but I cant find a means to lure the lines back to the open projects activities when displaying baselines.
Any ideas out there?
Many thanks,
Adrian.
Apologies if this issue has been raised before but with the PP search engine still down, I cant find a ready-made answer.
Has anyone found that P6.0 will display relationship lines amongst the baseline bars and milestones instead of the open projects bars and milestones? I cant find an option to force P6.0 to show relationships amongst the open project/s if Im displaying any type of baseline as well.
Ive found that any Gantt chart view options that include one or both of the primary baseline bars and primary baseline milestones will attract the relationship lines away from the open project bars and milestones.
The same happens for project, secondary and tertiary baselines.
Its very, very irritating but I cant find a means to lure the lines back to the open projects activities when displaying baselines.
Any ideas out there?
Many thanks,
Adrian.