Problem With schedule Percent Complete

1 reply [Last post]
Amir Arjmandi
User offline. Last seen 2 years 32 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 3
Hi
I have a problem with Schedule Percent complete.I can not get summarize percent In activity views, the P3E 5.0 or 6.0 doesn’t summarize schedule percent complete in WBS level and i can see it in activities level. also if i import a project from P3, software summarizes and shows it,automaticaly.
Thanks for your time.
Bye

Replies

Arnold Puy
User offline. Last seen 9 years 12 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Amir,

Schedule % Complete does not roll up in summary band if:

1. The Resource’s Price/Unit equal to Zero (0).

2. If you assign Baseline to your project, make sure that all resource assignments you’ve made is the same as that with the current especially "Cost".

3. Make sure that Budgeted Cost for both current & baseline schedule is greater than Zero (0).


Regards,

Arnold