Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

First Update P6 Schedule.

10 replies [Last post]
Shahzad Ahmad
User offline. Last seen 14 years 39 weeks ago. Offline
Joined: 14 Feb 2008
Posts: 96
Dear All

I need to confirm beofre making any mistake to update my Schedule.

i have made a simple Schedule without resource .

all activity are Task depant..
Activity type : fixed Duration & units.

Duration type is: duration.

i want to update based on my Physical % which is i am obtaing thro my progress mesurement sheet.

what i am going to do is i will tick Actual start date and putting physical % ... after that press F9 to see the result.

Do i need to change Duration type before update?

Do i need to change remaing duration while putting Physical % say 10%...

Please advise me in simple way to avoid confussion.

Thanks
Shahzad

Replies

Shahzad Ahmad
User offline. Last seen 14 years 39 weeks ago. Offline
Joined: 14 Feb 2008
Posts: 96
Hi Alex

Could yoy please advise me Calculation tab...
what are the changes are required for Manually updating.

Based on Physical %

"how to set aotu compute actual setting" i wan to turn off it.

it is showing tick in my P6 and deactivate...

my schedule is without resource.

Reg.
shahzad

Alex Wong
User offline. Last seen 11 years 5 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
Abeer

2 possible cause of double the duration
1 is assoicated with Resource loading calculation and Activity type
2 is project setting
There are 2 options when you set up your project

1. Remaining Duration = Original Duration + Actual Duration
2. Remaining Duration = Original Duration - Acutal Duration

HTH

Alex
mimoune djouallah
User offline. Last seen 4 years 40 weeks ago. Offline
Joined: 14 Oct 2006
Posts: 388


yes, i think original duration must each time be revised using the actual trend, for example:

activity : excavation 1000 m3
Expected productivity : 100 M3/ day then
Original duration OD = 1000/100 = 10 DAYS

when the activity begin you find after let’s say 1 week, that the actual productivity is 50 M3/ DAY thus you will have to change OD according to your actual trend.
OD = 1000/50 = 20 DAY
RD = 20- 7 = 13 DAYS
Physical % complete = 7*50/1000 = 35 %

of course you must keep a baseline before doing anything

HTH
MIMOUNE
Shahzad Ahmad
User offline. Last seen 14 years 39 weeks ago. Offline
Joined: 14 Feb 2008
Posts: 96
ANOON

yes my friend your advise is valid.

i allready assign base line...even i have kept one exported files for any bad luck....

Thanks
Shahzad
Abeer Mahmoud
User offline. Last seen 7 years 45 weeks ago. Offline
Joined: 8 Jul 2008
Posts: 87
Hi Alex,

Did you mean by (3. Update any revised duration) that I revised original duration?
And kindly note that when I made schedule I noticed that for activities which was started and not finished yet the duration at compilation was duplicated I wonder why?

Regards,

Abeer
Anoon Iimos
User offline. Last seen 2 years 15 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
I may suggest to establish the baseline schedule first before making any update.
Alex Wong
User offline. Last seen 11 years 5 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
Hi Shahzad

If that is the case then I will recommend the sequency of update

1. Update activity is already finished with a actual finish and actual start date
2. Update activity is start but not finish with a actual start date and Physical % complete and Remaining Duration
3. Update any revised duration
4. Reschedule the data date to the update data date

HTH

ALex
Shahzad Ahmad
User offline. Last seen 14 years 39 weeks ago. Offline
Joined: 14 Feb 2008
Posts: 96
HI ALEX

% complete type is "Physical"

1. Manual Update


Thanks
shahzad
Shahzad Ahmad
User offline. Last seen 14 years 39 weeks ago. Offline
Joined: 14 Feb 2008
Posts: 96
HI ALEX.

Thanks now i understand i have to put Physicasl % complete and remaining duration.
( for activity which is under progress)

my doubt was that i have to put only phy.% complte not remaining duration. ( as we use to do in P3)

Thanks for your advise.

Reg.
shahzad
Alex Wong
User offline. Last seen 11 years 5 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
Question for u

What is the % Complete type

And how you want to drive your remaining duration.

1. Base on Physcial progress
2. Manual Update
3. 0/100 rule
...

This will affect the forecast finish date of your schedule

HTH

Alex