Hi, Im using P5 and here is the issue:
I have a working schedule (lets call it L1) wherein the "Budgeted labor units" is 131203 hrs.
I have a baseline schedule (lets call it B1) wherein the "Budgeted labor units" is 130701 hrs.
Now, I assigned B1 to my L1 schedule and used it as a project baseline of L1. Looking at L1 schedule, how come my "BL Project Labor units" becomes 130581 hrs?? It should be the original budgeted labor units of B1 which is 130701 hrs, right?
The "Variance - BL Project Labor units" is showing -622 hrs, it should be (131203 - 130701) which is -502 hrs! How come?? Where does the extra 120 hrs comes from??
To double check, I then removed (or you can call it restored/separated) my baseline B1 schedule from my L1 schedule, and it really shows that the baseline schedules Budgeted labor units is really 130701 hrs, not 130581 hrs.
Pls help. Thanks in advance
Replies