Ver 5.0: Budgeted Labor Units of Baseline Schedules

1 reply [Last post]
Amar Aghana
User offline. Last seen 11 years 49 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 103
Friends,

I wish to increase the Budgeted Labor Units of Baseline Schedules by 25% of all the projects(75 Projects) by global change.

I am not able to select the appropriate field in the global change.

Any suggestions please??

Replies

Andrew Godfrey
User offline. Last seen 4 years 5 weeks ago. Offline
Joined: 11 Jul 2005
Posts: 18
Groups: None
Is it not BL Project Labor Units in Global Change?