Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Labor and non labor resourses

5 replies [Last post]
mariya Mariya
User offline. Last seen 12 years 28 weeks ago. Offline
Joined: 23 Dec 2009
Posts: 6
Is there a way to replace labor resource with nonlabor globaly? I’ve got a bunch of equimpment assigned as labour.

Replies

Kannan I
User offline. Last seen 14 years 17 weeks ago. Offline
Joined: 19 Dec 2009
Posts: 5
Groups: None
Hi Maria

Please go through the following procedure.

For example Labor resource ’L’ and you want to replace by Non labor resource ’N’ with same units. So create one user defined field ’X’ in ’Activity resource assignment’ window.

Go to the global change
1. Where ’Resource ID Name’ equals ’L’
then ’X’ equlas ’Remaining Units/time’
For using this global change, we stored the Labor resource units into the userdefined field. Aplly and Save this changes

Secind Global change
2. Where ’Resource ID Name’ equals ’L’
then ’Resource ID Name’ equals ’N’
and ’Remaining Units/Time’ equlas ’X’
Apply the changes hope this will change the resource assignment.

Regards
Kannan.I
Arnold Puy
User offline. Last seen 9 years 12 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Mariya,

You are correct. P6 does not allow you to change the resource type. Why don’t you try to apply my steps. I used to apply these steps every time I want to change my resource type and it works perfect to me. Otherwise, send a copy of .xer file and I’ll try to fix it for you.

Regards,

Arnold


mariya Mariya
User offline. Last seen 12 years 28 weeks ago. Offline
Joined: 23 Dec 2009
Posts: 6
Hello all!
Thank you for advises :-)
P6 does not allow to change resource type if the resource is already assigned to activity.Tried it.
And I’ve got wrong resource type assigned to activities in several projects across entire data base, and when I restore archive projects P6 brings wrong resource back to dictionary (:-
Arnold Puy
User offline. Last seen 9 years 12 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Mariya,

Welcome to Planning Planet.

Unfortunately, you can’t replace resource type using global change.

Try the following steps:

1. Create a new resource with resource type "Nonlabor".
2. Assign the newly created resource to your activities or if not, you can just simply export the resources to excel and simply change the "Resource ID" with the newly created resource.
3. when done, export it back to Primavera.

Regards,

Arnold
Anbin Ponnith
User offline. Last seen 8 years 5 weeks ago. Offline
Joined: 8 Jun 2009
Posts: 158
Dear Mariya,

In the Resource tab. Filter for all resources.

In column area make display Resource type.

Now change only the first resource as non-Labor.After which select the number of resources you need using Shift-select and use the option fill down.All the resources selected changes to non labor.

Regards,

Anbin Ponnith