Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How do you avoid having negative float?

10 replies [Last post]
ladi sodipo
User offline. Last seen 7 years 15 weeks ago. Offline
Joined: 6 Nov 2007
Posts: 27

When i load my project into P5 from MSP and start putting in actuals, some tasks start having negative float, this is not the case when i build out my plan, but once i start putting actuals, i start getting negative float, Is there a way i can stop this from happening or better still correct the negative float.

Thanks.

Replies

Stephen Devaux
User offline. Last seen 14 weeks 2 days ago. Offline
Joined: 23 Mar 2005
Posts: 667

Anning Sofi wrote:

"This is not a simple computer exercise to tweak the programme so there will be no delay. You have to identify the cause of the delay, and have your organization work out ways to recover from slippage"

Right on, Anning.  Negative float is how the software tells the user that something is projected to delay your project. Any time you have negative float, you have to identify what's causing it (work slippage, NET constraints, resource insufficiencies...) and what you're going to do about it (extend the project duration or recover the schedule and change the work plan).

If you had Spider Project or MS Project instead of Primavera, the way to go about recovering the schedule would be quite starightforward: determine which activities (or constraints) have how much Critical Path Drag, reduce the amount of their Drag and thus the length of their path, see if the CP goes elsewhere and where the Drag is on the new CP, reduce those Drags, etc.  It's not always the easiest thing to DO, but the data regarding the possible options is very straightforward to generate.

The failure of Primavera to compute Critical Path Drag is a huge shortcoming.  With projects of fewer than 200 activities, it is simple enough to compute Drag "manually" -- but on larger projects, it can be extremely time consuming, requiring a lot of work for each iteration.

Fraternally in project management,

Steve the Bajan

Anning Sofi
User offline. Last seen 5 years 34 weeks ago. Offline
Joined: 22 Jan 2012
Posts: 89
Groups: None

When you say you are putting actuals, and the programme starts gving you negative float, what that means is that there is delay? Why would you remove them? This is not a simple computer exercise to tweak the programme so there will be no delay. You have to identify the cause of the delay, and have your organization work out ways to recover from slippage

Raymund de Laza
User offline. Last seen 27 weeks 6 days ago. Offline
Joined: 22 Nov 2009
Posts: 762

Hi Mr. Hilal,

There is (-1349) days Total Float on your reply. Mr. Ladi requres the reply before 1349 days.

 

Cheers....

Hilal Hallani
User offline. Last seen 12 years 2 weeks ago. Offline
Joined: 3 Nov 2011
Posts: 16
Groups: GPC Qatar

Hello Ladi,

If you have any constraints (which I hope you dont) you need to remove them. In project details, your "must finish by" date must match your finish date in your programme. This should work, if it doesnt, then you need to reorganise your logic.

Regards

ladi sodipo
User offline. Last seen 7 years 15 weeks ago. Offline
Joined: 6 Nov 2007
Posts: 27
Interesting, Thanks Ya’ll.
Andrew Dick
User offline. Last seen 8 years 10 weeks ago. Offline
Joined: 14 Feb 2007
Posts: 295
Maybe get a job in the BD department?????

They’re optimistic little buggers, and always say that we have heaps of time to deliver a $1Bn job in 6 weeks with 2 blokes from the corner pub, two shovels and a meat pie...
Stuart Atkinson
User offline. Last seen 1 year 7 weeks ago. Offline
Joined: 16 Jan 2004
Posts: 68
Negative float may be appearing when activities are updated and are starting sooner than the logic tells. That is,
if you update the task woth a start date and the preceding task which it is dependant on has not finished, negative float will be created. They are out of the original sequence. Hope it helps.
Alex Wong
User offline. Last seen 11 years 6 days ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
I call this cosmatic planning - How can you avoid having negative float ... impossible ... unless the project dont have a deadline ....
Satya Narayana
User offline. Last seen 10 years 13 weeks ago. Offline
Joined: 29 Apr 2008
Posts: 47
Negative float is the other way of expressing the delay, if you do not want that remove the constraints and ur updated project goes beyond the planned project completion date.
Zhang Haixiang
User offline. Last seen 3 years 24 weeks ago. Offline
Joined: 14 Apr 2005
Posts: 250
Groups: None
check you schedule and find out the constraints, and remove them.