Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

What is Remaining Float?

2 replies [Last post]
Burak Evrenosoglu
User offline. Last seen 11 years 4 weeks ago. Offline
Joined: 26 Nov 2008
Posts: 4
Groups: None
Hi,

P6 has a new float field called "Remaining Float".

Remaining Float is calculated as the difference between the Late Finish and the Remaining Early Finish. Therefore the Remaining float will be equal to the total float when the activity is unstarted.

If the activity is in progress and user manually changes the Remaining Early Finish and the schedule will show a remaining float different than total float. However the schedule calculation will recalculate the Late Finish. Remaining Float will equal to Total Float once again.

1) Does anyone know what the "remaining float" is used for?
2) Is the "Remaining Float" ever a different value than the total float?

Thanks
Best Regards
Burak

Replies

David Kelly
User offline. Last seen 1 year 38 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
Since remaining float is based on the remaining early start, it will be different from total float if the project has been resource leveled.
Anoon Iimos
User offline. Last seen 2 years 14 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
here are my guesses:

1. Remaining Float = Total Float (for all Baseline / Target Schedules - which are not updated or progressed ever)

2. Total Float(s) changes once the schedule is updated or progressed not exactly as planned. Once activity or task is completed, its total float becomes zero.

3. Therefore, Remaining Float(s) is a variable figure that goes with the updates, and mathematically the same as Total Float(s).