activity date not changing

3 replies [Last post]
Shahzad Ahmad
User offline. Last seen 14 years 40 weeks ago. Offline
Joined: 14 Feb 2008
Posts: 96
Hi all

In P6 schedule an activity having 5 activity as a predecessor one of in all ready in progress and one is Constraints which is fouandation ready for Instal...

predecessor Constraints activity starting
date is 29 Jun 09* ( Activity DC00100)

successor of above actvity is Installation of equipment.
(activity EQ001010)

which will be start on 29 jun-09

I have links ss with Activity DC00100 with 0 lag as (predec)after schedule f9

i am wondering activity EQ001010 start date is 20 april 09

can any one advise why it is so...

Thanks
shahzad


Replies

Kashif Khan
User offline. Last seen 10 years 19 weeks ago. Offline
Joined: 17 Nov 2011
Posts: 46
Groups: None

i am not clear on ur statement but .....you should check if the activity has constraints ,otherwise if you want your desired date then play with lags + or -.

Patricia Le Clainche
User offline. Last seen 9 years 25 weeks ago. Offline
Joined: 18 May 2007
Posts: 86
Groups: None
Hello,

Some information are missing before giving you a answer :
- Which kind of relationship do you have for the other 4 predecessors ?
- Is it logical to get 5 predecessors if one is SS ? Maybe links are not correct ?

Best regards.
Patricia


Ali Farhat
User offline. Last seen 13 years 43 weeks ago. Offline
Joined: 23 Oct 2008
Posts: 120
Groups: None
I am not sure I followed you, please clarify more.