Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to sync Activity Dates & Resource dates

2 replies [Last post]
Rama Krishnan
User offline. Last seen 6 years 44 weeks ago. Offline
Joined: 2 Nov 2006
Posts: 14
Resource start & finish dates are not in line with activity start & finish dates.

I have a problem - when I extend activities resources assigned do not follow the activities.
I use a Non Labour resource. So by I have to default it to Non driving resource.

Is there a way to sync the resource dates & activity dates together. I prefer activity to drive the resource than the other way round for my application.

I also have a funny problem - When I drag the activity to change finish dates using mouse the resource assigned doe not follow. But instead I manually update the planned duration the resource follows & is in sync.

Anybody experiencing this problem?

All my activities are FixedDuration/Units setup. Resource assigned is one resource but non-labour. I have assigned a non -linear curve to the resource.


Rama

Replies

Rama Krishnan
User offline. Last seen 6 years 44 weeks ago. Offline
Joined: 2 Nov 2006
Posts: 14
Thanks
Wasantha, It works
Wasantha Nanayakkara
User offline. Last seen 6 years 45 weeks ago. Offline
Joined: 15 Oct 2003
Posts: 9
Groups: None
Rama
Try to tick the ’’drive activity dates’’ in the resource tab.I think this will solve your problem.

wasantha