Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Data date change, critical path changed?

2 replies [Last post]
anissa madewa
User offline. Last seen 10 years 34 weeks ago. Offline
Joined: 21 Aug 2013
Posts: 7
Groups: None

Hi,

I have a fixed schedule from previous project and I want to use it on another project with exact same activities, relationship, and everything. But when I changed the data date, the critical path also changed. Does anyone know why is this happening? Is this normal?

Thanks

Replies

Ronald Winter
User offline. Last seen 3 years 5 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None

Anissa,

Oh course that is normal.  The critical path often changes over the course of a project.  If it did not, there would be little use in tracking the entire project. 

Delays, low productivity, added work, changed conditions, changed workplans all combine to make the job of scheduling a complicated, rewarding experience.  Good luck!

Gary Whitehead
User offline. Last seen 4 years 46 weeks ago. Offline

Anissa,

Two obvious things to check:

Calendars. Changing the data date may have brought some non-worknig time into play on near-critical activities which has made them critical.

Constraints: If you have any constraints in the schedule, the dates of these constraints will not have shifted when you changed the data date. You will have to manually adjust / remove them.

 

Cheers,

 

G