Transfering projects from one machine to another.

1 reply [Last post]
Mangesh Khuspe
User offline. Last seen 27 weeks 11 hours ago. Offline
Joined: 10 Apr 2007
Posts: 162
hi
all
if we have stand alone installations of p5 on two different machines, and we are transfering the projects from one to another.

what should be the process, coz when i try to import it updates the whole project and the projects takes whatever data date in in old and starts new project from there.
can anyone explain how to use check in and check out facilitis in p5.

thanks in advance

cheers
mangesh

Replies

Niek Zonneveld
User offline. Last seen 2 years 1 week ago. Offline
Joined: 17 Mar 2005
Posts: 188
Groups: None
Mangesh,

The check out function basically just locks a project for modifications, avoiding errors resulting from the same data being altered at two different locations.

If you check in the project again, one of the options is to reschedule after import. That could explain your ’issue’.

H.T.H.