How to Change WBS Sequence

4 replies [Last post]
Kelly Randolph
User offline. Last seen 17 years 25 weeks ago. Offline
Joined: 13 Apr 2006
Posts: 13
I have imported a project from Primavera 5.0 into P3 and the WBS got out of sequence. How Can I restore to the original WBS order?

Thanks,
Kelly

Replies

Alex Wong
User offline. Last seen 11 years 6 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
Kelly

ANother dump way of doing it is export the WBS number
Delete the items that is out of sequencey
Add back the WBS item to the correct location
and Import back the WBS assignment

HTH

Alex
Kelly Randolph
User offline. Last seen 17 years 25 weeks ago. Offline
Joined: 13 Apr 2006
Posts: 13
I guess I should have thought about it a little more but I should be able to create activity codes that mirror the WBS and then use the group/sort by function to get the order I want. Yes or NO?


Kelly
David Kelly
User offline. Last seen 1 year 39 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
OOPS, that was the way you do it when you move from P3 to P5. There is NO way to change the sequence of the P3 WBS, other than the ASCII collating sequence (e.g. alphabetical order)
David Kelly
User offline. Last seen 1 year 39 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
Use the "indent/outdent" buttons on the extreme right of the WBS screen. Any WBS sorted output foillows the sequence of the WBS that you create in the WBS screen