Initial programme included within contact was not rescheduled before issuing

3 replies [Last post]
Matthew Klinefelter
User offline. Last seen 4 years 11 weeks ago. Offline
Joined: 11 Apr 2019
Posts: 4
Groups: None

Ive come across an interesting issue on a project where we have a programme included within our contract (NEC3). This programme had not been rescheduled prior to being included within the contract and as such the dates are not in line with the logic and constraints contained within the programme. Once rescheduled the dates are changed significantly.

My opinion on this is that a programme is more than the depiction of the dates and activities and should be reviewed and assess once it has been rescheduled as this is how the programme is operating in line with the logic and constraints written. The unscheduled version of the programme is in error as the dates are not working in line with the logic and constraints. Would be interested in others thoughs on this please and any case studies/additional information would be great.

Thanks in advance

Replies

Matthew Klinefelter
User offline. Last seen 4 years 11 weeks ago. Offline
Joined: 11 Apr 2019
Posts: 4
Groups: None

This was a programme produced by a contractor and written into our subcontract not something that has been submitted for acceptance. Thanks for the clarity.

Zoltan Palffy
User offline. Last seen 4 weeks 23 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

Mike is correct 

The constrains in the schedule shoule be contractual ones. Either Contractual milestones or if you are give release dates for certain areas. ALL CONTRACTUAL

Mike Testro
User offline. Last seen 5 weeks 2 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Matthew - Welcome to Planning Planet.

Just admit the mistake and submit the corrected programme.

And while you are at it take those constraints off - they shouldn't be there.

Best regards

Mike Testro