Re-scheduling and re-sequencing of activities
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Ronn,
The proper way and good practice of maintaining the schedule is reflecting the true sequence and correct methodology on site to make it a realistic schedule but make sure that baseline is preserve. The use of baseline is to compare the actual reflection on site vs target. Make sure all changes are documented and approved to make it easier to trace back the history. If the baseline is totally out of the blue from current schedule then make a suggestion or an effort to change the baseline and reflect the actual methodology and sequences maintaining the original baseline milestone date and contractual key deliverable date if possible. Make sure that new baseline is approved by the both parties (client and your management) before using the new baseline. If the critical path is change then make sure that the new critical path is agreed by both parties and not deviating contractual issues.