Activity sequencing & duration estimates
Mike,
you wrote that It is not good PP etiquette to liven up long dead topics.
Why?
It is interesting to look at new solutions of old problems. The software is developing and may suggest solutions that did not exist earlier, new methodologies may be applied, etc.
I think that it is interesting to compare what people think now and what people thought earlier, what solutions are suggested now in comparison with earlier proposals.
Best Regards,
Vladimir
Hi Ian
Welcome to Planning Planet.
Congratulations! You now hold the record in responding to long dead topics. 11 years old.
It is not good PP etiquette to liven up long dead topics.
Best regards
Mike Testro - Moderator
An interesting topic, my view is that its not good practice for any planner/scheduler/planning engineer to work alone, just as you wouldn't want the QS to produce the price in isolation or you wouldn't let design calcs or drawings go unchecked.
Its always best to keep a good record of where programme information has come from eg a big folder of emails, marked up programmes and contract dates (i.e subcontractual completions, client mandates etc). These records cover you as a planner should things go wrong and are essential for commercial claims and lessons learned.
At the end of the day, the more realistic and accurate the programme you start with, the less work there is for us with reschedules and changes (always good!) and the more stability the project will have.
I think in this situation, a Top down approach is most appropriate. Firstly, engineers dont understand the important of a schedule, they dont understand the concept of relationship, sequencing, or duration estimates. Once you have a top level schedule and telling them they will only have 2 week to come up with a final design. Then they will screaming for more time. It is then an opporturnity to ask for why... What is it involved in the design. Then they will explain ....
By going though this excise the plan will become their project plan. Yes scheduler/planner do have the initial task of understand the scope of work in accordance with the contract plus all the critical dates stated in contract. Once all these dates are ploted and the high level schedule is give to the individual team players. The will come back with their inputs very quickly (Usually) if that still doesnt work then you should have a team meeting to discuss their duration of finish their part of the works. That will usually create some thought after that meeting
Good Luck
Alex
As per activity sequencing that goes through experience.
Its a nice tread to participate. In my previous company we had excellant Planning Practice, there we, planning engineers, were responsible for preparation of method statements for all works in line with the BOQ weightages.
If u will execute this task for your schedule automatuically you will get all the links, dependancies and criticalities about your schedul.
I will appreciate your comments on this practices.
Cheers & Regards,
Rahul Shamrao Mulik
Ill list the process that we follow for preparation of a schedule:-
1. Read the scope of work .BOQ and the special condition of contract.
2. If it is a specialist work, consult someone with prior experience for the sequence of activities and probable duration.
3. Once the schedule is prepared, discuss it with the execution team.
4. After refinement, call in for a Schedule finalization meeting where we discuss the practicality of the schedule.
5. When everyone agrees to it, finalize it as a Baseline schedule.
6. During construction phase, if its decided to deviate from Baseline schedule, I incorporate it in my schedule and release it as new baseline.
I hope this helps,
Regards,
Suraj
Replies