ERROR while importing progress from excel

2 replies [Last post]
arun mathews
User offline. Last seen 9 years 18 weeks ago. Offline
Joined: 3 Nov 2014
Posts: 8
GuysPlease look into the following error report and tell the way aroundi was trying to update progress from excel file and import is unsucessfull..I know est_wt feild is associated with activity steps..but i am not using any..but y still P6 is asking for it? Excel Import log started : 01-Dec-14INFO: Importing Global Data...INFO: Importing Project Data...INFO: Importing: INFO: Saving: ERROR: est_wt is null for TASK ActivityID: D0001, Project: 141a-Updt-BLR4ERROR: est_wt is null for TASK ActivityID: DA1F0001, Project: 141a-Updt-BLR4ERROR: est_wt is null for TASK ActivityID: DA1F0010, Project: 141a-Updt-BLR4ERROR: est_wt is null for TASK ActivityID: DA1F0020, Project: 141a-Updt-BLR4ERROR: est_wt is null for TASK ActivityID: DA1F0030, Project: 141a-Updt-BLR4ERROR: est_wt is null for TASK ActivityID: DA1F0100, Project: 141a-Updt-BLR4 Thanks in advance Arun Mathews

Replies

Raymund de Laza
User offline. Last seen 32 weeks 5 hours ago. Offline
Joined: 23 Nov 2009
Posts: 762

Suggest to check the Percent Type of Activities. It must be Physical.

Zoltan Palffy
User offline. Last seen 4 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

where did you get the excel file that you are importing  ?

create an excel file to populate with your updated information by exporting the fields that you want this give you a template.

also go to the project mode big button on the left and make sure that you projetc is highlighted 

click on the calculations tab 

on the left make sure that Activity Percent complete based on activity steps is NOT checked