Base Line

2 replies [Last post]
Mohideen safi
User offline. Last seen 31 weeks 1 day ago. Offline
Joined: 10 Aug 2012
Posts: 3
Groups: None

hi anybody can answer

I updated my progress in P6 and i want this updated shedule as a new baseline. How can i change it in primavera P6?

 

Replies

Mohideen safi
User offline. Last seen 31 weeks 1 day ago. Offline
Joined: 10 Aug 2012
Posts: 3
Groups: None

thanks gary

Gary Whitehead
User offline. Last seen 23 weeks 4 days ago. Offline

Create a copy of your updated programme, and re-name it something like "Baseline -data date"

 

Then Open your original programme, go to Project > Maintain baselines > Add > Convert another project > select your new baseline

Once that is done, go to Project > Assign baselines > select your new baseline from the drop-down list under whichever baseline type you want to assign it to (Project, primary, secondary, or tertiary)