Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Baseline dates

3 replies [Last post]
Manoj VS
User offline. Last seen 8 years 26 weeks ago. Offline
Joined: 30 Jun 2009
Posts: 9
Groups: None

Hai,

Is there any chance to change start / end date of base line in P6

When I assigned a baseline start date / end date shown different.

Can anybody advice me?

Thanks in advance

Replies

Shah. HB
User offline. Last seen 18 weeks 11 hours ago. Offline
Joined: 25 Nov 2008
Posts: 773

Hi

you can change the baseline to meet the project requirement after incorporating ,make sure you first maintain baseline and then assign baseline to respective project

Raymund de Laza
User offline. Last seen 30 weeks 6 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Manoj,

Seems you assigned a baseline which is the current project and not the baseline project you added.

Check if you added a baseline project

>>> Project>>>Manage Baseline

>>>Assign Baseline>>select the right baseline you added

 

Hope this will solve your problem.

Regards,

Dieter Wambach
User offline. Last seen 6 years 51 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350

Manoj

It depends on what you want to modify. Projects--> Maintain BL:

- You can update a BL with current values.

- You can restore --> modify --> (re-)assign.

With intention this needs a certain security level.

Regards

Dieter