Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

revised baseline date problem

No replies
Kannan CP
User offline. Last seen 3 weeks 3 days ago. Offline
Joined: 12 Jun 2008
Posts: 290
Groups: None

I have a project in p6 with a fixed baseline. after 25% of the project is finished, it was discussed and agreed to fix a new baseline from the current project,due to some issues. Now the the following problems i am facing;

1. Activities which are in progress have a planned finish date(from new target) not equal to the current finish date.

2. Then i understood that the planned finish date is showing the completion date, at the time when the activity actually started. (since the new target was taken from the current project)

3. In order to make it correct, i export P6 to excel and copy/paste the current dates in the planned columns and import it. But this didn't work. I need to submit the schedule to Client very urgently

Can some one advise how to fix it?

 

Thanks in advance

 

Regards

Kannan