When I put actual start date, activity percent complete, lactual abour units remains 0, remainig unit and at completion do not match budgeted, wrong summaries, group totals, why? Is it wrong settings in calculations or something else?
Actual activity percent complete, but zero labor units percent complete. Why? Wrong settings?
Forum Sponsor
Top Posters
EViLL1
1 posts
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
HI, MARIA,
P6, Think is not matching, probably after you put percentage,you level your schedule.this sometimes cause the problem, specially in P6
Thanks,
Hi Mariya
I hope you are talking about P6.0
If yes, Then you have to decide on your settings for
(i) % complete type
- Physical
- Units
-Duration
(ii) Activity Duration type
- Fixed Units
- Fixed Units/ time
- Fixed Duration & Units
- Fixed Duration & Units/ time
I am not clear with your situation but I feel a setting with a combination of - (i) Units with (ii)Fixed units/time would give you what you are looking for.
With P3.0 the setting are different, a lot simpler but would not handle the variations in data input.
And about Grand Totals summaries, P6 uses Global default clendar to calculate summaries. So check what your Global Calendar settings are...
Best Regards
Shareef A Azeez