Imported Material Resources Duration set to zero

1 reply [Last post]
Mohamed El Turky
User offline. Last seen 8 years 5 weeks ago. Offline
Joined: 8 May 2013
Posts: 5
Groups: None

Hi Everyone, 

i just imported a programme, i discovered that duration of material resources are set to zero unlike the activities durations, any advice ?

Best regards,

Replies

Alain De leon
User offline. Last seen 7 years 41 weeks ago. Offline
Joined: 15 Jun 2012
Posts: 18
Groups: None

check the activity type on the activity details -select task dependent