When I put actual start date, activity percent complete, lactual abour units remains 0, remainig unit and at completion do not match budgeted, wrong summaries, group totals, why? Is it wrong settings in calculations or something else?
When I put actual start date, activity percent complete, lactual abour units remains 0, remainig unit and at completion do not match budgeted, wrong summaries, group totals, why? Is it wrong settings in calculations or something else?