Reason for the change FF>TF?

3 replies [Last post]
Shah. HB
User offline. Last seen 1 year 25 weeks ago. Offline
Joined: 25 Nov 2008
Posts: 773
Hi to all

I checked a schedule and i found for an activity FF [Free Float]
is greater than TF [Total Float] but in general FF lesser than Total float.

Is there any reason for the change in the condition?

Replies

Shah. HB
User offline. Last seen 1 year 25 weeks ago. Offline
Joined: 25 Nov 2008
Posts: 773

Many thanks Umar & Anwar

I got the solution for the raised query
Umer Mehmood
User offline. Last seen 3 years 2 weeks ago. Offline
Joined: 19 Jun 2008
Posts: 26
some times in this problem happen when you changed your calculation mode preference , especially when open ended activities are consider critical while scheduling

Hope this will help

Best REGARDS

UMER MEHMOOD
ABU DHABI
muhammad anwar
User offline. Last seen 4 years 47 weeks ago. Offline
Joined: 5 Feb 2007
Posts: 46
Groups: TILOS
Shahul,

If there is a must finish by constraint or mandatory finish pushing end earlier than what it should be will result in FF>TF. Check for the contraints and project finish date at project setting level.

Hope this will solve the problem.

regards

Muhammad