Hi,
I am trying to setup a way in Primavera P6 to help capture all the delay related information, like delay reasons and durations.
Delay Reason: I have come across "Delay Reason" activity code, but that will only allow me to provide a list of broad categories (e.g. Weather, Labor, Missing Material). So, I would also prefer to be able to create subcategories (e.g. under labor have subcategories of rework, absent perssonel, etc.) that are tied to Broad categories. Is this possible in P6, or if the tool doesn't have any feature like that, what would be the best workaround for that.
Delay Duration: Our scheduling team currently captures all the information regarding delays by creating "delay activities" and linking those a predecessors to delayed activities. This doesn't seem to be a sustainable way of do it. Is there a better way to capture delay duration info in P6?
Thanks!
Replies