Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Hi, everyone. What duration type you will choose? then what percentage type you will use to engage your duration type. Or it is

1 reply [Last post]
louis hung
User offline. Last seen 10 years 25 weeks ago. Offline
Joined: 17 Apr 2008
Posts: 10

 

Regarding you had completed resource loading and been authorized of your baseline.1.Fix Duration &Units2.Fix Duration &Units/time3.Fix units4.Fix Units/timeThen what percentage type you usually adopt.1.Duration2.Physical 3.Unit.Actually, I am not very sure how it engage this two elements to make it work well.Maybe you guy can provide your well experience here.Thanks!

Replies

Johannes Vandenberg
User offline. Last seen 11 weeks 2 days ago. Offline
Joined: 21 Jan 2010
Posts: 234

Hi Louis

If your schedule if resource loaded i suggest that you use Physical percentage type. The advantage is that you can spit the remaining duration and the % completion. This is particularly useful when you apply Earned Value Techniques. The disadvantage is that you have to update every single activity and apply remaining duration and % complete.  

Johannes