Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Effort driven vs resource driven

4 replies [Last post]
Lucas l
User offline. Last seen 13 years 39 weeks ago. Offline
Joined: 13 Mar 2010
Posts: 37
Groups: None
When I am comparing the two, can I say that effort driven means it is task dependent and resource driven is resource dependant.

For most constuction programme, which one is the more appropiate ?

I have some misunderstanding and doubts on these 2 terms. Can someone enlight me on this ?

Replies

Lucas l
User offline. Last seen 13 years 39 weeks ago. Offline
Joined: 13 Mar 2010
Posts: 37
Groups: None
Thanks all for the reply
Stephen Devaux
User offline. Last seen 20 weeks 6 days ago. Offline
Joined: 23 Mar 2005
Posts: 667
The sensitivity of an activity’s duration to resource addition is called its "resource elasticity". It’s an important characteristic for a planner to now, but it’s not very easily handled in software.

In the Total Project Control process, it’s managed by getting a second duration estimate: the Doubled Resource Estimated Duration, or DRED. If an activity is estimated to take 20D with a given load of resources, how long would it take if the resources are doubled. Possibilities include 10D ("perfectly resource elastic"); 12D (more common than 10D in most non-construction activities); 16D; 20D ("not resource elastic at all"; or 30D (installing the avionics in the cockpit of a jet fighter). Such variations are the sort of thing that there’s really no "automatic" ways of managing this.

If the scheduler has the DREDs for each activity, when s/he sees which activities are on the CP with lots of DRAG, looking at the DREDs of each activity helps show where resources and funds might most profitably be targeted.

Fraternally in project management,

Steve the Bajan
Rodel Marasigan
User offline. Last seen 3 hours 13 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Lucas,
Task dependent use activity calendar and drive resource. Recommended setting is to used Fixed Duration and Unit or Fixed Duration and Unit/Time. Using this duration type ignore driving resources regardless Drive Activity dates by default is tick. This is the most commonly used activity type in planning with or without resources.

Resource dependent use resource calendar and recommended setting is to used Fixed Unit/Time or Fixed Unit. Resource dependent requires resource assigned and control activity behavior when Drive activity dates by default is selected.
Shah. HB
User offline. Last seen 21 weeks 4 days ago. Offline
Joined: 25 Nov 2008
Posts: 773
Hi Hui

It depends on the nature of activity used in the project .There might be some activity where loading resources more could make the work get it done.Eg.Fixing Pipe in a room

Other depends on duration regardless of the resource the activity used Eg.Curing of structures