Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

"Within" vs "No Later"

3 replies [Last post]
Sophia M
User offline. Last seen 14 years 5 weeks ago. Offline
Joined: 10 Mar 2010
Posts: 10
Groups: None
If a contract calls for an activity to be submitted withing X days or no later than X days, then how can you schedule it (P6) without using constraints?

Replies

Samer Zawaydeh
User offline. Last seen 5 years 10 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Sophia,

All of these are normal Finish to Start Activities. That means that the Successor will start only after the Finish of the Predecessor.

The second example is not a must. It is a condition. After material submittal, you have shop drawings and procurement. So the 30 days might not be enough.

With kind regards,

Samer
Sophia M
User offline. Last seen 14 years 5 weeks ago. Offline
Joined: 10 Mar 2010
Posts: 10
Groups: None
Hi Samer,

Thanks for the reply.

For instance, if you have to submit a submittal within 14 days of the notice to proceed would be one example.

The other would be submittal must be submitted and approved 30 days before commencing the relevant construction activity.

No negative lags are allowed.
Samer Zawaydeh
User offline. Last seen 5 years 10 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Sophia,

You are left with 4 types of relationships and 2 ties.

Relationships: FS, SS, FF, SF
Ties: Lead and Lags

Usually the Contract Specifies LEVEL 1 schedules milestones. Milestones are activities with zero durations and resources.

What you are describing are Constraints. So if you can be more specific about your Contractual Requirement, maybe we can assist.

With kind regards,

Samer