Indrect cost for Defining Budget & at later stage for EVA

Member for

14 years 4 months

Thanks Gary;

Suppose We have a Planning Department. Account Code 0001. Now this Department will be responsible planning & monitoring of 10 Projects. Now while making Budget should I distribute the cost as lumsum using hammock?

Secondly during updating , is it better idea to "check" the "Auto compute actuals" box in resources so that this indirect costs fill automatically with time?

Member for

16 years 7 months

Process is not hard:

-understand the various indirect costs that will apply

-estimate the costs per time period of each of these costs

-estimate when and for how long these costs will be incurred

-Load them onto activities

 

eg:

project planner, £300 per day (full time), required full time for 1st month, 50% from then until end of construction.

or:

Procurement manager, £40 ph, 8 hr/day, required 1 day/week from commencement of tender evals, full time from commencement of tender negotaitions, down to 1 day/week once all orders are placed, zero after final delivery.

 

Typically indirect costs are loaded onto LOE / hammock type activities

 

Is there anything specific you are not sure about?