Maintain Multiple Baseline with 1 step

2 replies [Last post]
Rami Louka
User offline. Last seen 11 weeks 6 days ago. Offline
Joined: 22 Nov 2019
Posts: 3
Groups: None

Hi Guys,

I am dealing with window analysis with a lot if windows/projects/updates to compare, so here is my question:

How can I maintain multiple baselines to project in 1 step?? 

Again: I want to maintain two or three project to my current opened project in 1 step (1 click), is there a way sto select multiple projects and maintain them as baseline in 1 step?

 

Thanks for the help

Replies

Zoltan Palffy
User offline. Last seen 3 days 13 hours ago. Offline
Joined: 13 Jul 2009
Posts: 3078
Groups: None

its a 2 step process you can compare up to 3 baselines

1st select project maintain basleine then select assign baseline 

do this for up to 3 baselines 

Rodel Marasigan
User offline. Last seen 22 hours 49 min ago. Offline
Joined: 25 Oct 2006
Posts: 1685

Hi Rami,

That is not possible because the database only accept one at a time maintaining baseline and the same with assigning Baseline.