Multiple Baseline Units

No replies
Huss PS
User offline. Last seen 46 weeks 2 days ago. Offline
Joined: 2 Aug 2022
Posts: 7
Groups: None

Hi All,

 

I have 2 baselines and i need to compare the Labour units for both with the current schedule. 

How can i get the labour units for both of these baselines?

From below snapshot under "Units" both of the highlighted options are giving the same value.

 

TIA.

Zoltan Palffy
User offline. Last seen 4 weeks 6 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

you can have up to 3 different baselines

david kelly
User offline. Last seen 1 hour 24 min ago. Offline
Joined: 12 Feb 2016
Posts: 33
Groups: None

The colums BL project Labour Units and BL1 project labour units. You have to declare a Project and  Primary (BL1) baseline in the Assign Baselines dialogue

Huss PS
User offline. Last seen 46 weeks 2 days ago. Offline
Joined: 2 Aug 2022
Posts: 7
Groups: None

Huss PS
User offline. Last seen 46 weeks 2 days ago. Offline
Joined: 2 Aug 2022
Posts: 7
Groups: None