Hi Guys,
I am dealing with window analysis with a lot if windows/projects/updates to compare, so here is my question:
How can I maintain multiple baselines to project in 1 step??
Again: I want to maintain two or three project to my current opened project in 1 step (1 click), is there a way sto select multiple projects and maintain them as baseline in 1 step?
Thanks for the help