Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Doubt P6 - At Complete versus BL Project

5 replies [Last post]
Helder Rodrigues
User offline. Last seen 4 years 33 weeks ago. Offline
Joined: 30 Aug 2019
Posts: 4
Groups: None

Hello,

I have a doubt:

Schedule "A" has an At Complete of 7.94% in July / 19 before being entered as the baseline for Schedule "B".Its Ok for me...But after schedule "A" is entered as baseline on schedule "B" the field "Cum BL Project Nonlabor Units" has a% of 7.61%What am I doing wrong? 
6973
duvida_2.png

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

then get access to it or talk to the adminstrative person who does have rigths to this

Raymund de Laza
User offline. Last seen 32 weeks 7 hours ago. Offline
Joined: 23 Nov 2009
Posts: 762

Suggests to Set the Planned Dates equal to Current Dates.

Helder Rodrigues
User offline. Last seen 4 years 33 weeks ago. Offline
Joined: 30 Aug 2019
Posts: 4
Groups: None

Hello Zoltan, 

 

I don't have access to Admin menu 

 

Is there another solution to this problem?  Regards,

Helder Rodrigues
User offline. Last seen 4 years 33 weeks ago. Offline
Joined: 30 Aug 2019
Posts: 4
Groups: None

Hello Zoltan, 

I don't have access to Admin menu Is there another solution to this problem?  Regards,
Zoltan Palffy
User offline. Last seen 4 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

go to

Admin 

Admin Preferences

go to the Earned Value tab 

at the bottom where it says Earned Value Calculation When calculating value form a baseline use

change this to Budgeted value with current dates or At completion values with current dates