Forum Sponsor:

An innovation in P6 Professional training from RPCuk in partnership with Oracle. All the topics that matter to you in workshops customised to your role and industry.  Now get superior training value when you book our Blended Learning Bundle. Learn more here.

Viewer for .xer, xml and xls schedule files Schedule Reader™Free Trial

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Doubt P6 - At Complete versus BL Project

5 replies [Last post]
Helder Rodrigues
User offline. Last seen 1 week 5 days ago. Offline
Joined: 30 Aug 2019
Posts: 4
Groups: None

Hello,

I have a doubt:

Schedule "A" has an At Complete of 7.94% in July / 19 before being entered as the baseline for Schedule "B".Its Ok for me...But after schedule "A" is entered as baseline on schedule "B" the field "Cum BL Project Nonlabor Units" has a% of 7.61%What am I doing wrong? 
6973
duvida_2.png

Replies

Zoltan Palffy
User offline. Last seen 12 hours 58 min ago. Offline
Joined: 13 Jul 2009
Posts: 2402
Groups: None

then get access to it or talk to the adminstrative person who does have rigths to this

Raymund de Laza
User offline. Last seen 1 day 8 hours ago. Offline
Joined: 23 Nov 2009
Posts: 698

Suggests to Set the Planned Dates equal to Current Dates.

Helder Rodrigues
User offline. Last seen 1 week 5 days ago. Offline
Joined: 30 Aug 2019
Posts: 4
Groups: None

Hello Zoltan, 

 

I don't have access to Admin menu 

 

Is there another solution to this problem?  Regards,

Helder Rodrigues
User offline. Last seen 1 week 5 days ago. Offline
Joined: 30 Aug 2019
Posts: 4
Groups: None

Hello Zoltan, 

I don't have access to Admin menu Is there another solution to this problem?  Regards,
Zoltan Palffy
User offline. Last seen 12 hours 58 min ago. Offline
Joined: 13 Jul 2009
Posts: 2402
Groups: None

go to

Admin 

Admin Preferences

go to the Earned Value tab 

at the bottom where it says Earned Value Calculation When calculating value form a baseline use

change this to Budgeted value with current dates or At completion values with current dates