Hello,
I have a doubt:
Schedule "A" has an At Complete of 7.94% in July / 19 before being entered as the baseline for Schedule "B".Its Ok for me...But after schedule "A" is entered as baseline on schedule "B" the field "Cum BL Project Nonlabor Units" has a% of 7.61%What am I doing wrong?