Fix earned value at period end

6 replies [Last post]
Peter Barlow
User offline. Last seen 10 weeks 3 days ago. Offline
Joined: 13 Jul 2017
Posts: 2
Groups: None

Hello

Is there any way that when the data date is moved on and progress is updated that the earned value at previous period end remains fixed at what it was. For example, an activity that was 90% complete at year end will always have 90% earned at that date.

 

Thanks in advance.

Replies

Zoltan Palffy
User offline. Last seen 3 days 21 hours ago. Offline
Joined: 13 Jul 2009
Posts: 1472

thats if you are using physcial % complete

Morne Johann Bees...
User offline. Last seen 5 weeks 4 days ago. Offline
Joined: 25 Feb 2016
Posts: 10
Groups: None

I would hazard that the remaining duration has an effect here. The % calculation will depend on how much time has been expended versus the remaining. If you change the data date you should manually update remaining duration.

Morne Johann Bees...
User offline. Last seen 5 weeks 4 days ago. Offline
Joined: 25 Feb 2016
Posts: 10
Groups: None

I would hazard that the remaining duration has an effect here. The % calculation will depend on how much time has been expended versus the remaining. If you change the data date you should manually update remaining duration.

Zoltan Palffy
User offline. Last seen 3 days 21 hours ago. Offline
Joined: 13 Jul 2009
Posts: 1472

after the update is totally done select tools store period performance 

make sure to set up your financial periods 

Peter Barlow
User offline. Last seen 10 weeks 3 days ago. Offline
Joined: 13 Jul 2017
Posts: 2
Groups: None

I have been advised to do this but when the data date is advanced and the activities progressed the earned value at previous periods is still changed.

Zoltan Palffy
User offline. Last seen 3 days 21 hours ago. Offline
Joined: 13 Jul 2009
Posts: 1472

tools store period performance