Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Hours per TIME pERIOD

2 replies [Last post]
moutaz aldeib
User offline. Last seen 15 weeks 1 day ago. Offline
Joined: 31 Dec 2003
Posts: 278
Groups: None

Dear Planners,

I have a project calendar, which is 6 days a week and 8 hrs/day, when I checked the hours per time period by clicking the button, I found hours/week is 40 not 48 and the hours/month, and hours/year as well have not been changed. So I have to change it manually. How it changes automatically once I change the hours per day?

Regards,

Moutaz

Replies

moutaz aldeib
User offline. Last seen 15 weeks 1 day ago. Offline
Joined: 31 Dec 2003
Posts: 278
Groups: None

Dear Muhammad,

Thanks a lot for your reply, the project defauly calendar are already changed from the begining.

Regards,

Moutaz

muhammad anwar
User offline. Last seen 15 weeks 4 days ago. Offline
Joined: 5 Feb 2007
Posts: 46
Groups: TILOS

Dear Moutaz,

 

By changing projects default calendar the activity calendar does not change. If your activities are on 5 days calendar then they will stay on 5 day calendar but new activities you put in the project will pickup the new 6 day calendar. Diplay column for calendar and use fill down option to change the activities calendar and it will solve the issue.

 

Regards

Muhammad