Dear Planners,
I have a project calendar, which is 6 days a week and 8 hrs/day, when I checked the hours per time period by clicking the button, I found hours/week is 40 not 48 and the hours/month, and hours/year as well have not been changed. So I have to change it manually. How it changes automatically once I change the hours per day?
Regards,
Moutaz