P5 - User Preference - Hours per Time Period

Member for

24 years 6 months

Primavera basically calculates in hours. The displayed activity summary durations in days and weeks etc are calculated from factors in the User Preferences and therefore not all activity durations in days will display correctly when a project has multiple calendars with different hours per day for each calendar. Only activities where the assigned calendar hours per day matches the User Preferences will display the correct duration in days. P3 did not have this problem but SureTrak and MSP does. Asta has neatly programmed this issue out of PowerProject. Therefore different users will see different durations in days for activities in the same schedule when they have different User Preferences or when your client imports a schedule and has different User Preferences.



There is only one calendar for calculating all durations of Projects in the Projects workspace and WBS Nodes which is the default calendar checked in the Calendar form. Therefore when a project has very different calendars to the database Default Calendar is it unlikely that the durations of the Projects in the Projects workspace and WBS Nodes are likely to correct. It would be better for Primavera to calculate these summary durations based on elapsed durations or start and finish dates over a calendar assigned to a Nroject or WBS Node. The current situation does not allow any level of confidence of project or WBS Node durations.



Paul E Harris

Eastwood Harris Pty Ltd, Melbourne, Australia

Planning and Scheduling Training Manual & Book Publishers & Consulting

www.eh.com.au

Member for

18 years 6 months

I have summaries that show a completely different total duration then what the task sequence should add up to. All calendars are linked correctly, I am assuming it might be the settings mentioned earlier. Like in MS Projects, Tools Options Calendar settings, you can also set the hrs p/d, p/wk and p/mnth, if you change the durations there, it will affect your task and summary durations.

Member for

19 years 1 month

i’m also not sure (to be honest); it seems that P5/P6 only considers an "8 hr/day work" when counting total durations irregardless of the specific calendar used. ..