Percent on Completed Miestone Activity

1 reply [Last post]
Katie Coombs
User offline. Last seen 6 years 41 weeks ago. Offline
Joined: 24 Jun 2013
Posts: 9
Groups: None

Hi,

I have a schedule with milestone activities that are complete but are showing only 0% complete.  It is only happening to some of the milestone activities and not others.  Percent complete type is Physical, its a start Milestone and both started and finished boxes are ticked (actualized).

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

when you say showing 0% complete is that physical or duration % complete

look at the duration type what is it ?